By March 16, 2017, 267 supports out of 595 provided for by the project were ready, including 204 supports of the road bridge. There are more than 160 supports in operation.
39 spans of road and railway bridges were assembled out of 593 provided for by the project. This is more than 28.2 thousand tons of metal structures out of 230 thousand tons. More than 70 spans are in operation.
Work on the installation of a reinforced concrete slab for the carriageway of the road bridge is being carried out on the Taman side and on the island of Tuzla in a total of 26 supports. 5 thousand m3 out of almost 63 thousand are ready.
The assembly of arched spans is carried out at the technological site in Kerch. More than 6 thousand tons of metal structures out of almost 10 thousand tons were collected.
Almost 1.5 thousand various technical equipment are involved in the work, including almost 100 cranes of various lifting capacities, and hundreds of pieces of other equipment. Construction fleet - more than 30 units. Over the course of a month, more than 7 thousand builders work at the site, taking into account the rotation method. On average, more than 4 thousand people work at construction sites every day.